Good afternoon,

My name is Alicia and I’m part of the Communications team at Atlanta Gas Light. I am contacting you regarding a project within the NPU V area.

We are working on a pipeline replacement project which involves a portion of University Avenue, Pryor Road and Pulliam Street. The project work began last month. Residents along the project path received a notification letter prior to the start of construction.

The construction method being used is called “open cut.” This involves digging a trench in the road and placing the new pipe in the trench. This work will not impact customers’ gas service.

We will begin the Pulliam Street section later this month. Due to the nature of this work, we would like to ask that residents along the 900 block of Pulliam Street avoid parking on the street during the work. This phase of the work will take approximately 6 weeks. We wanted to contact you to make you aware of the work and to ask if you could help us communicate this update with the residents.

I attached the notification letter I mentioned to this email. I would welcome the opportunity to speak with you about this further.

Thank you,

Alicia Young
678-591-1434